Requalification and regulatory upgrade of the runway Lot 2 – 2nd Completion Phase of the "Marco Polo" Airport in Tessera - Venice.
The project will be developed in 7 phases throughout the years 2018, 2019 and 2020 for a total contract duration of 669 days.
By 2020 the requalification of the secondary runway will be completed.
This project features As-built in BIM.
The project includes the extension of RESA (Runway End Safety Area) which requires the construction of carryovers with claptrap of the sandbanks (lagoon areas - maritime works).