Search Results:
EAST PROJECT OF THE YARD ENI-SAIPEM FERRERA ERBOGNONE (PV)
-
Employer: ENI S.p.A.
-
Works amount: € 11.805.045,88
-
Works start: 01 November 2010
-
Works end: 20 August 2013
-
Works status: Completed
-
Show more...
“VIE D’ACQUA PROJECT” – EXPO/FAIR
-
Employer: EXPO 2015 S.p.A.
-
Works amount: € 16.000.000,00
-
Works start: 1 August 2013
-
Works end: 24 April 2017
-
Works status: Completed
-
Show more...
REALIZATION OF THE EXTENSION FOR THE SHOPPING CENTER AUCHAN IN MESTRE (VENICE)
-
Employer: Galleria Commerciale Italiana S.p.A.
-
Works amount: € 32.997.194,77
-
Works start: 18 July 2012
-
Works end: 24 November 2013
-
Works status: Completed
-
Show more...
Tunnel assessment operational activities on motorways a10, a7, a26 under the management of “1° tronco” genova.
-
Employer: Autostrade per l'Italia S.p.A.
-
Works amount: 4.650.000 EURO
-
Works start: 21/05/2020
-
Works end: 09/10/2020
-
Works status: Completed
-
Show more...
Logistic building constructionin Carpi (Mo)
-
Employer: Enel S.p.A
-
Works amount: € 6.651.691
-
Works start: 1 January 2018
-
Works end: 30 September 2019
-
Works status: Completed
-
Show more...
New fill tank for shipyard use inside the "porto petroli" of genoa sestri ponente
-
Employer: Comune di Genova
-
Works amount: 67.936.561,73 EURO
-
Works start: July 2021
-
Works status: In progress
-
Show more...
CONSTRUCTION OF P-117, VICENZA HIGH SCHOOL REPLACEMENT
-
Employer: DEPARTMENT OF THE NAVY, NAVAL FACILITIES ENGINEERING COMMAND
-
Works amount: € 28.330.000
-
Works start: 8 November 2019
-
Works end: in progress
-
Works status: In progress
-
Show more...
Construction of a new road in palizzi marina, lot 2 from km 49+485 to km 51+750 - second functional lot
-
Employer: ANAS S.p.A.
-
Works amount: 72.915.097,91 EURO
-
Works start: 15/06/2021
-
Works status: In progress
-
Show more...
CONSTRUCTION OF THE SERVICE ARCHITECTURE – EXPO 2015
-
Employer: EXPO 2015 S.p.A.
-
Works amount: € 54.489.301,24
-
Works start: 01 February 2014
-
Works end: 17 April 2015
-
Works status: Completed
-
Show more...
MONTECCHIO MAGGIORE TOLL STATION AND CONNECTING ROADS CONSTRUCTION
-
Employer: Autostrada Brescia Verona Vicenza Padova SpA
-
Works amount: € 56.813.343,42
-
Works start: July 2019
-
Works end: ongoing
-
Works status: In progress
-
Show more...
Total items found: 89