Search Results:
Special works for the derivation and definitive conveyance of the waters that flow into the Acquasanta within the industrial port of Palermo
-
Employer: Port Authority of Palermo
-
Works amount: € 17.391.200,00
-
Works start: 5 May 2008
-
Works status: Completed
-
Show more...
P655 P-8A HANGAR AND FLEET SUPPORT FACILITY AND P407 TRITON HANGAR AND OPERATION FACILITY – SIGONELLA (CT) ITALIA
-
Employer: NAVFAC Atlantic Division
-
Works amount: € 45.200.000
-
Works start: 12 December 2016
-
Works end: ongoing
-
Works status: In progress
-
Show more...
NOVI-VINODOLSKI MOTORWAY BYPASS ON THE A7 RUPA-RIKEKA-ZUTA LOVKA (PHASE 1)
-
Employer: HRVATSKE AUTOCESTE d.o.o.
-
Works amount: 63.180.400 EURO
-
Works start: 10/2021
-
Works status: In progress
-
Show more...
Design and construction of the Zagreb Pier Container Terminal - 1st Phase - Rijeka (Croatia)
-
Employer: Port Authority of Rijeka
-
Works amount: € 70.585.015,45
-
Works start: 1 June 2012
-
Works end: 2018
-
Works status: Completed
-
Show more...
DESIGN AND CONSTRUCTION OF THE HIGH-SPEED/HIGH-CAPACITY RAILWAY LINE - MILAN/VERONA SEGMENT
-
Employer: RFI (Italian Rail Network)
-
Works amount: € 191.747.899,53 linea MI-BS (€ 1.652.750.000,00)
-
Works start: 01 February 2012 (line MI-BS)
-
Works end: in progress
-
Works status: In progress
-
Show more...
DESIGN AND CONSTRUCTION OF 30 RESIDENTIAL UNITS AND 8 DIRECTIONAL SPACES (VENICE)
-
Employer: EST CAPITAL SGR – Società di Gestione del Risparmio SpA
-
Works amount: € 9.782.153,00
-
Works start: 26 January 2007
-
Works end: 31 January 2011
-
Works status: Completed
-
Show more...
Design & construction of the site adaptation works for the new euro hpc supercomputer in the tecnopolo di bologna area (lot 4)
-
Employer: CINECA, Consorzio Interuniversitario
-
Works amount: 55.090.864,55 € (importo a base d’asta)
-
Works start: April 2021
-
Works status: In progress
-
Show more...
EXECUTIVE DESIGN AND EXECUTION OF COMPLETION WORKS OF VICENZA RING ROAD- 1st PHASE - 1st SECTION
-
Employer: ANAS S.p.A.
-
Works amount: € 36.200.000
-
Works start: 1 March 2017
-
Works end: ongoing
-
Works status: In progress
-
Show more...
Executive design and execution of the consolidation work on the Trapezio Levante pier and the head of the Manfredi dock in the commercial Port of Salerno
-
Employer: Port Authority of Salerno
-
Works amount: € 24.867.548,34
-
Works start: 12 May 2011
-
Works status: Completed
-
Show more...
ENGINEERING, PROCUREMENT, CONSTRUCTION AND FINANCE FOR INFRASTRUCTURE DEVELOPMENT FOR PHASE 1 KONZA TECHNO CITY (KENYA)
-
Employer: Konza Technopolis Development Autority (KoTDA) - Kenya
-
Works amount: € 367.469.103
-
Works start: 16 June 2017
-
Works end: ongoing
-
Works status: In progress
-
Show more...
Total items found: 122