Ospedali, Alberghi e Musei

Ampliamento e ristrutturazione edificio di Via Ripamonti n.436 Milano

EXPANSION AND RENOVATION OF A BUILDING IN VIA RIPAMONTI N. 436 MILAN

  • European Institute of Oncology
  • Works amount: € 11.782.669,30
  • Works start: 30November 2009
  • Works end: 30 September 2011
  • Works status: Completed
Cern science gateway - nuovo centro visitatori

Cern science gateway - new visitor center

  • CERN
  • Works amount: 53.900.000 €
  • Works start: 02/11/2020
  • Works status: In progress
Costruzione dell'ospedale militare di al khoudh (oman)

MILITARY HOSPITAL CONSTRUCTION AL KHOUDH (OMAN)

  • Ministry of Defense
  • Works amount: € 46.373.970,00
  • Works start: 06 October 2015
  • Works end: 3 March 2019
  • Works status: Completed
Gardaland magic hotel

Gardaland Magic Hotel

  • Gardaland S.p.A.
  • Works amount: € 11.500.000
  • Works start: 15 February 2017
  • Works end: 31 May 2019
  • Works status: Completed
Museo M9 - Mestre – Venezia

MUSEUM M9 - MESTRE - VENICE

  • Polymnia Venezia S.r.l.
  • Works amount: € 39.546.955
  • Works start: 16 June 2014
  • Works end: 22 October 2018
  • Works status: Completed
Realizzazione fabbricato con destinazione alberghiera in piazza duca d'aosta a milano

CONSTRUCTION OF A BUILDING INTENDED FOR HOTEL USE IN PIAZZA DUCA AOSTA – MILAN

  • REALE IMMOBILI S.p.A.
  • Works amount: € 25.890.000
  • Works start: 7 March 2013
  • Works end: 31 July 2015
  • Works status: Completed
Realizzazione opere civili, finitura e impianti tecnologici di un albergo a Castelnuovo del Garda (VR)

REALIZATION OF CIVIL WORKS, FINISHING AND TECHNOLOGICAL SYSTEMS OF A HOTEL IN CASTELNUOVO DEL GARDA (VR)

  • Gardaland S.p.A.
  • Works amount: €  14.851.789,87
  • Works start: 30 September 2002
  • Works end: 5 July 2004
  • Works status: Completed
Residenza sanitaria assistenziale

HEALTH CARE RESIDENCE

  • I.R.A.
  • Works amount: € 15.538.754,27
  • Works start: 16 June 2007
  • Works end: 09 August 2009
  • Works status: Completed
Riqualificazione generale del complesso alberghiero denominato

General requalification of the hotel "The Big" in Milan

  • Unipol Sai S.p.A.
  • Works amount: € 22.084.000
  • Works start: 16 March 2018
  • Works end: October 2020
  • Works status: Completed