AUCHAN – SHOPPING CENTRE IN BUSSOLENGO (VR-ITALY)
AUCHAN S.p.A.
Works amount:
€ 19.274.000
Works start:
8 October 2015
Works end:
Completed
Works status:
Completed
“AUCHAN” MALL – RESTYLING AND EXPANSION PROJECT
Galleria Commerciale Italiana S.p.A.
Works amount:
€ 4.210.607,47
Works start:
28 September 2017
Works end:
6 September 2018
Works status:
Completed
SHOPPING CENTER PALLADIO – VICENZA
UNICOMM s.r.l. – Malo (VI)
Works amount:
€ 15.906.872,49
Works start:
18 November 1999
Works end:
21 July 2004
Works status:
Completed
SHOPPING CENTRE “METAURO” – EXPANSION AND RESTYLING INTERVENTION IN FANO (ITALY)
Auchan S.p.A.
Works amount:
€ 12.120.574
Works start:
02 December 2016
Works end:
10 Otcober 2017
Works status:
Completed
THERMAL CENTRE FORDONGIANUS – NUORO
Italian Region of Sardinia
Works amount:
€ 24.209.408,07
Works start:
5 June 1995
Works end:
2 July 2004
Works status:
Completed
MULTIFUNCTIONAL COMPLEX “ETNAPOLIS” - CATANIA
Alis Imobiliare C.T.A. S.p.A. – Belpasso (CT)
Works amount:
€ 140.500.000,00
Works start:
13 May 2003
Works end:
13 July 2006
Works status:
Completed
CONSTRUCTION OF THE RETAIL PARK MARKET DA VINCI
M.C.F. S.r.l.
Works amount:
€ 25.299.672,88
Works start:
12 July 2006
Works end:
18 October 2007
Works status:
Completed
CONSTRUCTION OF A MALL CALLED “AREA SERENISSIMA” - VICENZA
Maltauro Immobiliare Srl
Works amount:
€ 77.500.000,00
Works start:
April 1992
Works end:
December 2004
Works status:
Completed
Vicenza Fair Exhibition
Fiera di Vicenza S.p.A. – Immobiliare Fiera di Vicenza S.p.A.
Works amount:
€ 37.205.025,99
Works start:
13 February 2012
Works end:
02 January 2014
Works status:
Completed
WORKS FOR THE CONSTRUCTION OF AN ALIMENTARY DISTRIBUTION CENTER IN LOC. SANTA PALOMBA (ROME)
Fincedi Lazio S.p.A.
Works amount:
€ 7.385.000,00
Works start:
02 October 2006
Works end:
31 January 2008
Works status:
Completed
REALIZATION OF THE EXTENSION FOR THE SHOPPING CENTER AUCHAN IN MESTRE (VENICE)
Galleria Commerciale Italiana S.p.A.
Works amount:
€ 32.997.194,77
Works start:
18 July 2012
Works end:
24 November 2013
Works status:
Completed
Restoration and requalification of the former ice production center "La Rotonda"
SGR Tower
Works amount:
€ 7.150.000
Works start:
11 january 2018
Works end:
31 July 2019
Works status:
Completed
SHOPPING CENTRE “LE COTONIERE”
Salerno Invest - Le Cotoniere sr.l.
Works amount:
€ 48.000.000,00 RTI
Works start:
5 December 2015
Works end:
24 November 2016
Works status:
Completed
DEVELOPMENT OF COTOROSSI - VICENZA
Sviluppo Cotorossi SpA
Works amount:
€ 130.000.000
Works start:
January 2009
Works end:
30/04/2021
Works status:
Completed