Militare

Falcon 5 / f15 qa beddown project

Falcon 5 / f15 qa beddown project

  • U.S. Army Corps of Engineers
  • Works amount: 466.197.000 EURO
  • Works start: 30/06/2020
  • Works end: ongoing
  • Works status: In progress
Job order contract presso la base militare americana di Deveselu in Romania

Job order contract at Deveselu airbase, Romania

  • Navfac Europe Africa Southwest Asia
  • Works amount: € 16.000.000
  • Works start: 22 February 2017
  • Works end: 22 February 2022
  • Works status: In progress
Lavori civili

Civil Works

  • Ministry of Defense
  • Works amount: € 1.072.913.160
  • Works start: 1 July 2012
  • Works end: 8 July 2017
  • Works status: Completed
Lavori Civili, Infrastrutturali e Manutentivi

Civil, Infrastructural and Maintenance Works

  • LEONARDO S.p.A.
  • Works amount: Euro 182.533.291
  • Works start: 20/01/2022
  • Works status: In progress
Lavori di ristrutturazione Hangars n.1, 2 e 3 dell'aeroporto di Aviano

REHABILITATION WORKS FOR HANGARS N. 1, 2 AND 3 OF AVIANO AIRPORT

  • Ministry of Defense - General Directorate of Works and State Property
  • Works amount: € 12.527.617,00
  • Works start: 1 February 2007
  • Works end: 1 March 2013
  • Works status: Completed
MACC Djibouti: contratto quadro per la realizzazione di lavori nelle basi militari americane di Djibouti, Arica

MULTIPLE AWARD CONSTRUCTION CONTRACT DJIBOUTI

  • US Navy (NAVFAC ATLANTIC)
  • Works amount: € 35.000.000
  • Works start: 26 October 2018
  • Works end: ongoing
  • Works status: In progress
MACC Napoli: contratto quadro per la realizzazione di lavori nelle basi militari americane di Napoli

DESIGN-BUILD / DESIGN-BID-BUILD MULTIPLE AWARD CONSTRUCTION CONTRACT NAPLES

  • US Navy (NAVFAC EUROPE SOUTHWEST ASIA)
  • Works amount: € 16.756.000
  • Works start: 26 September 2018
  • Works end: ongoing
  • Works status: In progress
MATOC Vicenza: contratto quadro per realizzazione di lavori nelle basi militari americane di Vicenza

MATOC VICENZA (Multiple Award Task Order Contract)

  • US Army
  • Works amount: € 8.640.000
  • Works start: 10 July 2018
  • Works end: ongoing
  • Works status: In progress
Modifiche agli edifici esistenti per ospitare temporaneamente il Rafale (z-304-01)

MODIFICATIONS FOR AL-UDEID EXISTING BUILDING TO ACCOMODATE RAFALE TEMPORARILY (Z-304-01)

  • Qatar Armed Forces
  • Works amount: € 11.809.200
  • Works start: 19 September 2019
  • Works end: 30/03/2020
  • Works status: Completed
Nuovo stabilimento J.S.F. F35

NEW PLANT J.S.F. F35

  • Alenia Aeronautica S.p.A.
  • Works amount: € 213.782.665,40
  • Works start: 23 December 2010
  • Works end: 31 March 2014
  • Works status: Completed
P655 P-8A hangar and fleet support facility and p407 triton hangar and operation facility – Sigonella (CT) Italia

P655 P-8A HANGAR AND FLEET SUPPORT FACILITY AND P407 TRITON HANGAR AND OPERATION FACILITY – SIGONELLA (CT) ITALIA

  • NAVFAC Atlantic Division
  • Works amount: € 45.200.000
  • Works start: 12 December 2016
  • Works end: ongoing
  • Works status: In progress
Realizzazione della nuova High School nella base militare americana di Vicenza

CONSTRUCTION OF P-117, VICENZA HIGH SCHOOL REPLACEMENT

  • DEPARTMENT OF THE NAVY, NAVAL FACILITIES ENGINEERING COMMAND
  • Works amount: € 28.330.000
  • Works start: 8 November 2019
  • Works end: in progress
  • Works status: In progress
Realizzazione pista di volo

South Ramp, Zulu Arm/Dearm Pad, Expand North Ramp - Aviano Air Base

  • Naval Facilities Engineering Command Europe and Southwest Asia ROIC AVIANO
  • Works amount: € 8.667.056,00
  • Works start: 24 August 2004
  • Works end: 19 December 2005
  • Works status: Completed
Reprocurement of the collocated Club - Aviano Air Base (PN)

REPROCUREMENT OF THE COLLOCATED CLUB – AVIANO AIR BASE (PN)

  • U.S. Department of Navy Resident Officer in Charge of Contract (ROICC)
  • Works amount: € 15.354.812,38
  • Works start: 6 December 2001
  • Works end: 24 April 2004
  • Works status: Completed
Vicenza unaccompanied enlisted personnel housing (ueph) residenza per il personale militare

VICENZA UNACCOMPANIED ENLISTED PERSONNEL HOUSING (UEPH)

  • NAVFAC EURAFSWA
  • Works amount: € 18.400.000
  • Works start: 1 March 2016
  • Works end: May 2020
  • Works status: Completed

Gruppo ICM SPA - Copyright © 2018 - All Rights Reserved

Privacy e Policy

Gruppo ICM SPA - Copyright © 2018 - All Rights Reserved

Privacy and Policy