JUNCTION RAMP BALVANO AND NR407 BASENTANA

Bretella di Raccordo Balvano e SS407 Basentana

Functional completion works of the junction ramp connecting the city of Balvano and the road linking the industrial areas of Baragiano Scalo, Balvano and NR 407 Basentana.The works carried out in separate phases are still an integral part of one overall project and consist of:

  • Road Works for 19.24 km
  • Tunnels for 1.09 km
  • Viaducts in pre-stressed reinforced concrete and steel for 2.917 km
  • Miscellaneous works such as aqueducts, sewage systems

TECHNICAL SPECIFICATIONS

Employer: Ministero dell'Industria, Commercio e Artigianato - Gestione Separata Terremoto – Roma

Works amount: € 102.238.027,92

Works start: 29 April 1983

Works end: 12 January 2004

Copyright © 2018. All Rights Reserved Gruppo ICM SPA - 36100 - VICENZA Viale dell'Industria 42 Tel. 0444/336111 Fax 0444/961541 P.IVA - 02526350240 - Privacy e Policy
Powered by Tech&WebSolutions.it