INTERNATIONAL AIRPORT PRAIA (CAPE VERDE)

Progetto di espansione e qualificazione dell'aeroporto internazionale di praia - capo verde

Expansion and restructuring of the International Airport of Praia – Cape Verde

The main works to be performed are as follows:

  • foundations on plinths connected by concrete beams
  • Pillars a.c. upper part of the tax and installation of the truss roofing
  • Truss roof structure made of metallic carpentry galvanized, and painted
  • Coverage faced panels sandwich aluminum
  • Construction of a retaining wall made of reinforced concrete, to connect the new and the floor of the terminal HALL
  • Construction of two escalators
  • Construction of two elevators
  • Realization of a luggage conveyor in the same starting area
  • Masonry exterior and interior
  • Floors and walls in the new HALL
  • Floor and wall areas of the old airport
  • Aluminum-glass windows
  • Development of a new domestic and international baggage claim area
  • Realization of new parking areas close to the wall support
  • Extension works and functional testing water treatment plant
  • Renovation of the customs goods

TECHNICAL SPECIFICATIONS

Employer: Ministero delle Infrastrutture e delle Economie Marittime

Works amount: € 26.950.000

Works start: 21 april 2006

Works end: 31 May 2019