Realizzazione delle opere di completamento della nuova autostazione di montecchio maggiore e collegamenti con la viabilità ordinaria

MONTECCHIO MAGGIORE TOLL STATION AND CONNECTING ROADS CONSTRUCTION

  • Autostrada Brescia Verona Vicenza Padova SpA
  • Works amount: € 56.813.343,42
  • Works start: July 2019
  • Works end: ongoing
  • Works status: In progress
Realizzazione pista di volo

South Ramp, Zulu Arm/Dearm Pad, Expand North Ramp - Aviano Air Base

  • Naval Facilities Engineering Command Europe and Southwest Asia ROIC AVIANO
  • Works amount: € 8.667.056,00
  • Works start: 24 August 2004
  • Works end: 19 December 2005
  • Works status: Completed
Realizzazione tratto stradale Lushnje - Fier (Albania)

REHABILITATION OF THE HIGHWAY FROM LUSHNJE TO FIER – REPUBLIC OF ALBANIA

  • Ministry of Public Transport and Telecommunications, General Road Directorate / PIU
  • Works amount: € 19.484.020,61
  • Works start: 27 March 2006
  • Works end: 28 February 2009
  • Works status: Completed
Reprocurement of the collocated Club - Aviano Air Base (PN)

REPROCUREMENT OF THE COLLOCATED CLUB – AVIANO AIR BASE (PN)

  • U.S. Department of Navy Resident Officer in Charge of Contract (ROICC)
  • Works amount: € 15.354.812,38
  • Works start: 6 December 2001
  • Works end: 24 April 2004
  • Works status: Completed
Rete idrica e fognatura nelle città di Mindelo - Capo Verde

WATER SUPPLY AND SEWERAGE NETWORK PROJECT OF MINDELO TOWN – CAPE VERDE

  • Ministry of Infrastructure, Transport and Telecommunications Directorate General of Infrastructures
  • Works amount: € 8.561.172,74
  • Works start: 18  August 2008
  • Works end: 19 August  2010
  • Works status: Completed
Riabilitazione della strada Mahiu - Narok (Kenya)

REHABILITATION OF MAAI MAHIU-NAROK ROAD – N. RD/457 - KENYA

  • Ministry of Roads and Public Works - Kenya
  • Works amount: € 55.674.689,80
  • Works start: 02 October 2006
  • Works end: 09 June 2010
  • Works status: Completed
Riabilitazione della strada Mandela a Dar Es Salaam (Tanzania)

REHABILITATION WORKS OF MANDELA ROAD TO DAR ES SALAAM (TANZANIA)

  • Tanzania National Roads Agency (Tanzania)
  • Works amount: € 37.078.084,69
  • Works start: 01 May 2008
  • Works end: 21 July 2011
  • Works status: Completed
Riabilitazione e ricostruzione di due dighe sul Wadi al Qattarh (Libia)

DAM ON THE WADI AL QATTARAH - BENGHAZI (LIBYA)

  • General Popular Committee – General Water Authority – Dams Department
  • Works amount: € 52.178.317,88
  • Works start: 15 December 1998
  • Works end: 30 April 2004
  • Works status: Completed
Riabilitazione ed allargamento della strada di contornamento dell'isola di Fogo (Repubblica di Capo Verde)

REHABILITATION WORKS OF THE LOWER CIRCULAR ROAD TO FOGO ISLAND – CAPE VERDE

  • Ministry of Transport, Infrastructure and Telecommunications
  • Works amount: € 43.327.000,00
  • Works start: 01 March 2009
  • Works end: 14 June 2014
  • Works status: Completed
S.S. n. 421 dei Laghi di Molveno e Tenno: sistemazione nel tratto tra San Lorenzo in Banale e Loc. Nembia

N.R. NO 421 OF LAKES OF MOLVENO AND TENNO: ARRANGEMENT IN THE SECTION BETWEEN SAN LORENZO IN BANALE AND LOC. NEMBIA

  • Autonomous Province of Trento
  • Works amount: € 6.662.281,37
  • Works start: 13 July 2004
  • Works end: 19 March 2007
  • Works status: Completed
SS. 429 - Tronco Poggibonsi – Empoli

N.R. 429 - EMPOLI-POGGIBONSI SECTION - ITALY

  • ANAS S.p.A. Road Compartment to Tuscany
  • Works amount: €  58.312.131,00
  • Works start: 20 December 2002
  • Works end: 31 May 2012
  • Works status: Completed
Vicenza unaccompanied enlisted personnel housing (ueph) residenza per il personale militare

VICENZA UNACCOMPANIED ENLISTED PERSONNEL HOUSING (UEPH)

  • NAVFAC EURAFSWA
  • Works amount: € 18.400.000
  • Works start: 1 March 2016
  • Works end: May 2020
  • Works status: Completed
Webuye - Malaba Road - Lot NO.2

WEBUYE - MALABA ROAD - LOT NO. 2

  • Ministry of Roads and Public Works - Kenya
  • Works amount: Works amount  € 34.182.049,00
  • Works start: 1 March 2011
  • Works end: Completed
  • Works status: Completed

Copyright © 2018. All Rights Reserved Gruppo ICM SPA - 36100 - VICENZA Viale dell'Industria 42 Tel. 0444/336111 Fax 0444/961541 P.IVA - 02526350240 - Privacy e Policy
Powered by Tech&WebSolutions.it

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.

Ok